WP4 Piloting the digital platform and selected services

Green line

WP leader: Centria

Goal: The concrete development work of the platform (software development) and deployment. Piloting the functional level needs that emerged in TP1-3, research work and selected services based on the needs of companies (not full piloting).

Task Roles Schedule
T4.1 Implementation and development of the pilot platform main implementer Centria, limited contribution SeAMK and UVA 12/2024-7/2025
T4.2 Development of example services Centria 4/2025-7/2025
T4.3 Piloting example services Centria 6/2025-9/2025
T4.4 Joint development of example services (workshops) and further iteration with target groups Centria 4/2025-10/2025

Output: Report on the results of development activities and piloting